Once the cap frame returned from the galvanizers, the fly spears, back stays and handrails were welded in place and it now weighs 4.4 tons.
A sprinkler system was fitted throughout the mill and drying store. This enabled all five floors in the mill to be utilized for living purposes without the need of a fire escape. It will also enable us to use oak doors, rather than fire doors throughout the building.
We had to lift off the temporary roof so that the tanks for the sprinkler system could be fitted on to the very top floor. It’s surprising how much lighter the building appears with no roof.
Under-floor heating has also been fitted to all the upper floors as well as the ground floor. This has now been installed and boarded out with chipboard. The final flooring will be engineered oak glued to the chipboard.